Project at a Glance
Project details
- Location: Ojén
- Property: townhouse
- Solar panels: 12 × AIKO 510 W (6.12 kWp)
- Inverter: Growatt MIN 6000TL-XH2 hybrid inverter
- Battery storage: 5 kWh
- Mounting: traditional tiled roof, aluminium mounting structure; fixing points drilled and waterproofed
- Handover: legalisation and registration of the installation completed, certification provided to the client
- Surplus energy: we assisted the client with an electricity contract for surplus solar energy compensation
- Estimated savings: about €1,700 per year
- Estimated payback: about 3.5 years
Why This System Size
The system uses 12 AIKO 510 W panels (6.12 kWp) with a 5 kWh battery. We size every system from the electricity bill and the usable roof area measured on site.
If you are weighing storage for a similar home, see our guide on whether a battery is worth it, and our overview of solar panel installation in Ojén.
How We Did It, Step by Step
1. Survey and design
- We visit the property and measure the roof to see how much area is usable.
- We analyse the electricity bill to understand how much energy the home uses and when.
- We size the system from the consumption and the roof area.
2. Quote, contract and delivery
- We send a written proposal with the system size, equipment and price.
- After the contract is agreed, we deliver the mounting structure and the equipment.
3. Installation
- Mounting structure: aluminium structure on the traditional tiled roof, with the fixing points drilled and waterproofed.
- Panels and cabling: we installed the 12 panels and the DC and AC cabling.
- Protection: electrical protection devices were installed.
- Inverter and battery: the hybrid inverter and the 5 kWh battery were installed and connected to the property and the grid.
- Configuration: system configuration and monitoring setup.
4. Handover and monitoring
- Legalisation: we completed the legalisation and registration of the installation.
- Certification: the client received the corresponding certification.
- Surplus energy: we assisted with an electricity contract for surplus solar energy compensation.
Grants and Savings
Estimated savings for this installation are about €1,700 per year, with an estimated payback of about 3.5 years. Incentives depend on the municipality, the date and the call, so we confirm them case by case. See our guide to solar subsidies in Andalucía.
Aftercare Included
- 3-year warranty on the installation, extendable to 5 years after a free on-site inspection
- Panels and inverters are covered by the manufacturer warranties
- Monitoring set up for the system
Location: Ojén
Questions About This Project
It is a 6.12 kWp hybrid solar and battery system: 12 AIKO 510 W panels, a Growatt MIN 6000TL-XH2 hybrid inverter and a 5 kWh battery.
We combine the usable roof area measured on site with the consumption shown on the electricity bill (how much and when the home uses energy). The system is then sized to fit both.
The panels sit on an aluminium mounting structure. The fixing points on the tiled roof were drilled, waterproofed and fitted with the structure so that it supports the array securely.
We assisted the client with arranging an electricity contract for surplus solar energy compensation. The price depends on the supplier and the contract, so we do not quote a general figure.
The estimated payback for this installation is about 3.5 years, with estimated savings of about €1,700 per year. It depends on consumption, the tariff, the surplus price and available incentives, so we calculate it separately for each property.
KiDi Solar gives a 3-year warranty on the installation, extendable to 5 years after a free on-site inspection. Panels and inverters are covered by the manufacturer warranties. Read the warranty policy.
Want a System Like This for Your Home?
Book a free survey. We visit your property, measure the roof, analyse your electricity bill and send you a written proposal with the system size, equipment and price.